目标Objective

Design and manufacture a complex 2K Cover. Critical lead time for this project: 40 days T0. 120 days mass production, Project done.

任务Tasks

28
研发
17
模具制造
10
注塑成型
30
箔膜研发
10
材料检验
5
产品改良
综述Overview

 

09/2021

Dongguan, China

Started to work on the frame cover.


10/2021

Dongguan, China

Mold Finished, T0 trial and test manufacture.

01/2022

Finished all tesing, start mass production.